September – RTD FasTracks East Rail Line News

September 12, 2013 RTD/Commuter Rail No Comments

http://www.stapletondenver.com/wp-content/uploads/East-Rail-Line-Header.jpg

View the September 2013 Newsletter – including the featured aerial photo tour +

Construction Completed

–  7 utility relocations, for a total of 182 including gas line lowering at Smith Road and Havana Street in Denver
–  Drainage box installations south of Smith Road between Albion and Dahlia streets in Denver
–  Girder sets over I-70 Flyover Bridge in Aurora
–  Construction of concrete platforms for track installation on Peña Boulevard Bridge in Denver

Construction Underway

–  Rail installation on the alignment along Peña Boulevard near Tower Road in Denver
–  Constructing concrete platforms for track installation along Smith Road at I-225 in Aurora
–  Smith Road reconstruction between Kearney and Albion streets in Denver
–  Station platform construction at all East Rail Line station sites

Upcoming Construction

–  Roadway reconstruction on the north side of Sable Boulevard at Smith Road in Aurora
–  Roadway reconstruction at York and Josephine streets at 40th Avenue in Denver
–  Railroad crossing track and gates installation at Smith Road and Havana Street in Denver
–  Intersection reconstruction at Chambers and Smith roads in Aurora

For more project information: rtd-fastracks.com