September 2014- RTD FasTracks East Rail Line News

September 4, 2014 RTD/Commuter Rail No Comments

http://www.stapletondenver.com/wp-content/uploads/RTD News September.jpg

DOWNLOAD THE SEPTEMBER 2014 EAST RAIL LINE NEWS

Construction Completed

-Installation of corridor protection barrier wall along Smith Road between Colorado Boulevard and Dahlia Street in Denver

-Asphalt paving at the 40th/Colorado Station on Jackson Street and 42nd Avenue

-Pedestrian bridge erection at the 38th/Blake Station which will connect the Park-n-Ride to the station

Construction Underway

-Canopy installation at the Central Park Station platform

-Track construction and decking installation on the nearly 5,000-foot long I-70 Flyover Bridge in Aurora

-Utility relocations and roadway repaving at the 38th/Blake Station Park-n-Ride on Wynkoop Street between 38th and 40th streets

Upcoming Construction

-Installation of overhead electrical wire to power the commuter rail trains along Smith Road in Aurora

-Reconstruction of 33rd Avenue between Moline and Peoria streets as part of the Peoria Station area work

-40th Avenue/Albion Street realignment between Colorado Boulevard and Smith Road in Denver

For more project information: rtd-fastracks.com