October – RTD FasTracks East Rail Line News

October 7, 2013 RTD/Commuter Rail No Comments

http://www.stapletondenver.com/wp-content/uploads/October East Rail Line News.jpg

View the October 2013 Newsletter

Construction Completed

– 186 total utility relocations including water line tie-ins at Smith Road between Forest and Dahlia streets in Denver
–  Rail installation between Tower Road and Peña Bridge
–  Painting at the 56th Avenue, Tower and E-470 bridges
–  Construction of concrete platforms for track installation along Smith Road under I-225

Construction Underway

–  Rail installation along Peña Boulevard approaching DIA in Denver
–  I-70 Flyover Bridge construction in Aurora
–  Albion Street reconstruction between Smith Road and Colorado Boulevard in Denver
–  Station platform construction at all East Rail Line station sites

Upcoming Construction

–  Roadway reconstruction on the north side of Sable Boulevard at Smith Road in Aurora
–  Roadway reconstruction at York and Josephine streets at 40th Avenue in Denver
–  Railroad crossing track and gates installation at Smith Road and Havana Street in Denver
–  Intersection reconstruction at Chambers and Smith roads in Aurora

For more project information: rtd-fastracks.com

 

Quick Links

Search

Follow Us!

Share This Page

Share on facebook
Share on twitter
Share on linkedin
Share on google
Share on email

View On Map

Print This Page

Share on print

This site uses cookies and similar technologies to improve your browsing experience and site functionality. By closing this banner, you agree to the use of cookies. Read more in our Terms of Use & Privacy Policy