November 2015- RTD FasTracks East Rail Line News

November RTD Construction Update banner

DOWNLOAD THE NOVEMBER 2015 EAST RAIL LINE NEWS

 Construction Completed

  • Placement of stairs and installation of elevator equipment for the 38th/Blake pedestrian bridge in Denver
  • Installation of visual rider screens at the 40th Ave. & Airport Blvd
  • Gateway Park and Peña Boulevard stations
  • Roadway, sidewalk and curb work on Blake Street at 38th Street in Denver

Construction Underway

  • Installation of landscaping and irrigation at the Peoria Station in Aurora
  • Testing of trains, gates and signals from Union Station to Denver International Airport. This work may cause delays at the railroad crossings along the CU A Line
  • Pedestrian pathway fencing placement at all project railroad crossing

Upcoming Construction

  • Installation of benches on the train platforms at the 38th/Blake, 40th/ Colorado and Central Park stations in Denver
  • Swing gate installation at the pedestrian crossing at the Peña Boulevard Station in Denver
  • System performance demonstration testing of the trains—operating CU A Line as it will function on opening day