November 2014- RTD FasTracks East Rail Line News

November 4, 2014 RTD/Commuter Rail No Comments

http://www.stapletondenver.com/wp-content/uploads/2014/11/RTD-East-Rail-update.jpg

DOWNLOAD THE NOVEMBER 2014 EAST RAIL LINE NEWS

Construction Completed

-Installation of vehicle detection loops and railroad crossing construction on Steele Street in Denver

-Erection of canopies at the Peoria Station commuter rail platform in Aurora

-Installation of permanent commuter rail alignment fencing on Smith Road between Dahlia and Holly streets

Construction Underway

-Roadway reconstruction on Chambers Road between 25th Drive and 32nd Avenue in Aurora

-Installation of canopies and electrical utility lines at the 38th/Blake Station in Denver

-Reconstruction of 33rd Avenue between Moline and Peoria streets in Aurora

Upcoming Construction

-Installation of the glass treatments on the pedestrian bridge at the 38th/Blake Station

-Multi-use trail construction between the 40th/Colorado Station and Albion Street

-Erection of canopies at the 40th/Colorado and 40th Ave. & Airport Blvd-Gateway Park stations

-Set final track on the I-70 Flyover Bridge in Aurora

For more project information: rtd-fastracks.com