Construction Completed

  • 6 utility relocations, including waterline relocations on Smith Road between Holly and Dahlia streets in Denver
  • Girder placement on the E-470 Bridge, east of Peña Boulevard
  • Installation of the drainage box at 40th Avenue and 40th Street in Denver
  • Grading of the track alignment along Peña Boulevard near 56th Avenue

Construction Underway 

  • Utility relocations and street reconstruction along Smith Road between Dahlia and Kearney streets
  • Peoria Station platform construction at Smith Road and Peoria Street in Aurora
  • Placement of overhead power poles along the track alignment in Denver
  • Grade preparation for track installation at Coors Field

Feature of the Month:

Sustainability on the Eagle P3 Project

The Regional Transportation District (RTD) and Denver Transit Partners (DTP) are committed to leveraging sustainable practices in the design, construction and operation of the Eagle P3 project. To DTP, sustainability means conducting business in a socially, economically and environmentally responsible manner to the benefit of current and future generations, thereby creating value for all of our stakeholders.

Click here to view the May 2013 Monthly Construction Newsletter 