June 2014 – RTD FasTracks East Rail Line News

http://www.stapletondenver.com/wp-content/uploads/ERL-News-June-Header.jpg

DOWNLOAD THE JUNE 2014 EAST RAIL LINE NEWS

Construction Completed

–  11 utility relocations in May 2014 for a total of 272 utility relocations on the project to date, including fiber optic 
relocations on 40th Avenue in Denver

–  Reconstruction of Sable Boulevard at Smith Road in Aurora
–  Commuter rail crossing installations at Clayton and Steele streets in Denver

Construction Underway

–  Reconstruction and installation of center medians on Dahlia Street, south of Smith Road, in Denver
–  Roadway repaving of Jackson Street and 42nd Avenue at the 40th/Colorado Station
–  Installation of track at the Denver International Airport solar panel farm

Upcoming Construction

–  Reconstruction of the intersection and railroad crossing of Chambers Road at Smith Road in Aurora
–  Pouring the concrete decking on the I-70 Flyover Bridge over Airport Boulevard in Aurora
–  Reconstruction of 40th Avenue, east of Colorado Boulevard, and Albion Street, south of Smith Road, in Denver

For more project information: rtd-fastracks.com