July – RTD FasTracks East Rail Line News

http://www.stapletondenver.com/wp-content/uploads/RTD FasTracks East Rail Line News June 2013.jpg

Construction Completed 

– 10 utility relocations, for a total of 168, including water line lowering on Smith Road and Havana Street
– Railroad crossing reconstruction on Clayton Street between 42nd and 43rd avenues
– Installation of traction power transformers at Sandown substation in Denver

Construction Underway

– Railroad crossing construction on Steele Street between 42nd and 43rd avenues in Denver
– Smith Road bridge repaving over Sand Creek in Denver
– Overhead power pole installation along Smith Road in Aurora
– Intersection reconstruction at Smith Road and Sable Boulevard in Aurora

Upcoming Construction

– Green Valley Ranch Bridge girder placement in Denver
– Rail installation on the alignment along Peña Boulevard
– I-70 Flyover Bridge pier column construction and girder settings in Aurora
– Road reconstruction at East 33rd Avenue and Moline Street in Aurora

Click here to view the July 2013 Monthly FasTracks Construction Newsletter