August 2014 – RTD FasTracks East Rail Line News

August 11, 2014 RTD/Commuter Rail No Comments

http://www.stapletondenver.com/wp-content/uploads/Header.jpg

DOWNLOAD THE AUGUST 2014 EAST RAIL LINE NEWS

Construction Completed
•  Installation of overhead catenary system wire to power the commuter rail lines along 78th Avenue
•  Reconstruction and installation of the railroad crossings at Dahlia and Ulster streets in Denver
•  Relocation of wet utilities at the 40th/Colorado Station at 42nd Avenue and Jackson Street
Construction Underway
•  Roadway repaving and utility relocations on Moline Street between 33rd Avenue and Smith Road
•  Reconstruction of the Steele and Holly streets railroad crossing in Denver
•  Track construction on the commuter rail alignment from Clayton to Steele streets
Upcoming Construction
•  Installation of canopies on the Peoria and Central Park station platforms
•  Installation of rail signal gates at the Havana Street railroad crossing
•  Corridor protection barrier construction along 40th Avenue in Denver
•  Relocation of utilities at Blake and 40th streets

For more project information: rtd-fastracks.com