April – RTD Fastracks East Rail Line News

http://www.stapletondenver.com/wp-content/uploads/Third Creek Bridge Photo_April East Rail Line.jpg

Construction Completed

  • 6 utility relocations in March 2013, making a total of 150 since beginning the project
  • Construction of the Sand Creek freight bridge in Denver
  • Girder placement over Peña Boulevard westbound lanes and median near DIA
  • Grading of the track alignment along Peña Boulevard near 56th Avenue
  • Girder placement on Tower Road commuter Rail Bridge

Construction Underway

  • Utility relocations and street reconstruction along Smith Road between Dahlia and Kearney streets
  • Overhead power pole foundation installation on Smith Road between Chambers Road and Airport Boulevard in Aurora
  • Decking on the Peña Boulevard Bridge near DIA
  • Grade preparation for track installation

VIEW ENTIRE APRIL NEWSLETTER +

For more project information: www.RTD-FasTracks.com/ec_1

Quick Links

Search

Follow Us!

Share This Page

Share on facebook
Share on twitter
Share on linkedin
Share on google
Share on email

View On Map

Print This Page

Share on print

This site uses cookies and similar technologies to improve your browsing experience and site functionality. By closing this banner, you agree to the use of cookies. Read more in our Terms of Use & Privacy Policy