RTD FasTracks East Rail Line News

January 14, 2013 RTD/Commuter Rail No Comments

http://www.stapletondenver.com/wp-content/uploads/Dec.-3-Est-Rail-Line-Image.jpg

 Upcoming Outreach

With the start of a new year, we are looking forward to another exciting period of construction and outreach. Here are some ways to keep in touch with the East Rail Line as construction moves along:

  • Look for our quarterly newsletter for information on the progress of the RTD Commuter Rail Project
  • Request a presentation about the East Rail Line for your neighborhood association or civic group by contacting the East Rail Line Public Information team at 303-297-5284
  • Visit www.RTD-FasTracks.com for up-to-date construction information, detour maps and project news

 Construction Completed

  • 126 utility relocations, including storm sewer relocations at Garfield Street and waterline relocations at Peoria Street and Smith Road in Denver
  • Construction and realignment of 41st Avenue at York Street
  • Girder placement on 56th Avenue commuter rail bridge east of Peña Boulevard
  • Overhead power pole foundation installation between Havana and Peoria streets

Read the January Newsletter +